Introduction and deliverables

Our project consists of three different deliverables:

  1. Creation of the game engine and the first version of the website with a delivery date of 30/03/2023.
  2. Creation of the beta version of the game with a delivery date of 11/05/2023.
  3. Creation of the final version of the game and the website with a delivery date of 15/06/2023.

Planification

If the project direction is composed of three main deliverables. Our planning is broken down into five major periods:

  1. Project initiation and kickoff ✅
  2. Creating the beta version of the game engine as well as working on the first version of the website ✅
  3. Completing the game engine to integrate all the tools to create the game as well as its functionalities
  4. With the help of the game engine, develop the expected levels and features requested by the players
  5. Deliver the final version of the game, after testing and minor improvements, as well as the final version of the website
15.03.2023
Project kickoff
30.03.2023
Beta version of the Game Engine and static website delivery
20.04.2023
End of Game Engine development
11.05.2023
End of Game development and release of first beta version
15.06.2023
Final website and final game version delivery and presentation

Key Objectives and Sprint definition

We will work using agile methodology, while being structured according to the key points of the project expressed above and our intermediate deliverables.

Our sprints have a duration of 1 week and upcoming tasks are planned for the next 2 weeks. Thus, at all times, our team knows the status and tasks to be performed for the current sprint as well as the n+1 sprint.

In addition to this, each sprint is defined by a key objective to understand the theme of the tasks to be performed. Below is the list and definition of sprints until final delivery of the project deliverables.

Logbook

Date Duration Taks Author
01.03.2023 04h00 Creation of beta game website and creation of three little games. Benoît
03.03.2023 03h00 Initial creation of the original game script Valendin and Benoît
01h00 Setup 3 repositories on GitLab for webiste, beta game and game Benoît
09.03.2023 02h00 Meeting: Coordination for setup the development environment on team members computer and internal discussion about the art game direction Group
02h00 Logo creation of the game Francesco
10.03.2023 03h00 Website initial creation and design from the template Francesco and Leticia
10.03.2023 02h00 Writing of the text content of the website Valentin
12.03.2023 01h00 Add template to all the pages Leticia
13.03.2023 01h30 Team meeting: Presentation JavaScript and Presentation Website(HTML and CSS) Group
15.03.2023 01h00 Added some text for the HTML page Valentin
22.03.2023 01h00 Team meeting: Define the task of each team member Group
02h00 Add dark/light mode on the website Leticia
23.03.2023 02h30 Create all flow page graphics Benoît
25.03.2023 03h00 Create and add content to "Description" page Francesco
26.03.2023 03h00 Create and add content to "Sketch" page Leticia
03h30 Create and add content to "Homepage" Valentin
02h00 Create and add content to "Flow" page Benoît
01h00 Team meeting: Check modification on the website Group
28.03.2023 02h30 Improve content of the "Homepge" Valentin
01h30 Team meeting: Help to improve the homepage Valentin and Benoît
01h00 Team meeting: Helpt to improve the homepage Valentin, Benoît and Leticia
10-30.03.2023 16h00 Designing and creation of the website, bug fixing Francesco
10h00 Designing and creation of the website, bug fixing Leticia
05h00 Bug fixing Benoît
40h00 Study, design and implementation of the game's JS code Benoît
31.03.2023 00h15 Remove unused ressourcees, code optimisation Leticia